Lowham Walsh furnished professional staff to direct construction activities for 5 major CBNG PODs in the Powder River Basin. Direction was provided to insure that design specification approved by the BLM were closely adhered to and met.  Lowham personnel provided expertise in the following areas:

  • Reviewed engineering plans and provided guidance for engineered and typical road sections, checked road sections for grade and width.  Checked cut and fill stakes for accuracy and proper placement.
  • Checked drill pad and slot cut locations per design requirements and location. Located drill hole locations.
  • Provided oversight of low-water crossings for designed grade, cross-sectional design area and oversaw placement of erosion control.
  • Contacted line-finders for utility locates prior to commencement of work.
  • Directed supply trucks to the proper areas and maintained inventory control.
  • Conducted daily safety meetings and gave daily job assignments and work areas.
  • Compiled and assembled project completion reports, which contained daily work logs, safety meeting reports and photographs.